250 MW TenneT Battery Energy Storage Project Moves Forward in Germany
Noveria Energy signed the grid connection construction agreement with transmission system operator TenneT Germany for a 250 MW battery energy storage system (BESS) project in Germany connecting in early 2028.
The project is in Niedersachsen in northwest Germany where large amounts of offshore wind energy from the North Sea connect to the grid.
Following the completion of construction, the project will be operated in accordance with the grid connection agreement and establishes the technical prerequisites to support grid stability and the integration of renewable energy in the future.
Battery energy storage systems are increasingly critical to managing growing shares of renewable generation and ensuring security of supply. Noveria continues to advance its strategy of developing a portfolio of large-scale infrastructure assets that support the energy transition and the resilience of the power system.
The project is part of Noveria’s broader development pipeline of over 3 GW of battery energy storage assets.
About the Author
T&D World Staff
Content Team
Nikki Chandler
Group Editorial Director, Energy
[email protected]
Jeff Postelwait
Managing Editor
[email protected]
Christina Marsh
Senior Editor
[email protected]
Ryan Baker
Associate Editor
[email protected]
Amy Fischbach
Electric Utility Operations
[email protected]
Rich Maxwell
Community Editor
[email protected]
Gene Wolf
Technical Editor
[email protected]