Transmission Line Rebuild

FirstEnergy Corp. is rebuilding a 13.3-mile section of an existing 138-kV transmission line connecting substations
Nov. 1, 2016

FirstEnergy Corp. is rebuilding a 13.3-mile section of an existing 138-kilovolt (kV) transmission line connecting substations in Fayette and Lyons to help enhance service reliability for more than 18,000 Toledo Edison customers in Fulton County.

The $16.5 million project includes replacing 334 poles in the existing right-of-way, along with stringing more than 13 miles of new wire. 

Following are images of the beginning of the rebuild.