Transmission planning has never been more necessary. It has also never encountered so much uncertainty.
Data center demand is accelerating fast, with load expected to reach 80 GW by 2030 and account for up to 12% of U.S. electricity use. Unlike the gradual load growth of the past, these facilities arrive in gigawatt-scale steps where land, power, fiber, and water align. Individual campuses now routinely request more than 1 GW, making location a decisive factor for dispatch, power flows, and upgrade needs. Traditional planning methods that rely on coarse forecasts or react to developer requests are not designed for this. They overlook the practical realities that determine where projects can reach notice-to-proceed (NTP) quickly, which risks overbuilding in the wrong places while missing the areas that most need attention.
We're already seeing the consequences of this in Texas. In August 2025, Hays County rejected a 200-acre data center near the Edwards Aquifer over water concerns. Yet the region had just undergone major grid upgrades, including reconductoring a 345 kV line intended to support load that may now never materialize. ERCOT itself acknowledged this challenge in its own 2024 Regional Transmission Plan: "The location of load is crucial in driving flow patterns and determining transmission needs...Planning practices and policies must be reviewed to address these new challenges."
A Land-First Planning Framework
To help utilities anticipate where large loads are most likely to materialize, we introduce a bottom-up, data-driven approach that mirrors developer goals and constraints and converts that into planning-grade load signals. By integrating buildable land availability, permitting constraints, and grid data, the framework identifies the regions where power can be delivered quickly and where transmission constraints stall development. ERCOT serves as the case study showing where targeted upgrades can unlock gigawatts of stranded potential.
The process has three steps.
- Identify where hyperscale sites can reach NTP fastest, ignoring grid capacity.
- Determine which of those locations have available headroom and which are limited.
- Translate findings into bus-level loads and targeted upgrade candidates that slot directly into standard reliability studies.
What We Found in ERCOT
Leveraging environmental datasets and power flow modeling, we screened all 13.8 million parcels in Texas using common developer requirements to map exactly where development can credibly occur:
- At least 100 acres of buildable land
- Suitable topography under 15 degrees
- Outside wetlands, floodplains, or conservation easements
- Favorable zoning
- Water availability (excluding drought-restricted counties)
- Proximity to fiber, gas, and 345 kV transmission infrastructure
This left 765,000 acres suitable for fast hyperscale development.
The land clusters tightly: only 230 substations across Texas have suitable land for data centers nearby. The top 10% of these substations hold over 30% of total buildable acreage. This concentration simplifies planning. Instead of preparing for load at thousands of potential points, planners can focus on a defined set of high-probability interconnection locations.
Using ERCOT's 2028 summer-peak planning case, we evaluated how much additional load each of these 230 substations could accommodate before any line or transformer exceeds N-1 thermal limits.
Only 17% of substations have positive withdrawal capacity today, mostly in Northwest and Central Texas, meaning they’re ready for growth. The remaining substations and surrounding land are effectively stranded by existing constraints.