In early 2019, a Dissolved Gas Analysis (DGA) was performed on all three single-phase 500 kV: 115 kV transformers at Tono Substation. One of the transformers was identified as nearing its end of life due to increased gassing to high levels After PSE’s need assessment and solution report were completed, planning and engineering worked on a design that led to the procurement of a new, state-of-the-art, transformer at the end of 2020.
Two and a half years later, after traveling several thousand miles across the country from Memphis, Tennessee via train and truck, the massive transformer arrived in Centralia, WA, in June 2023. PSE took delivery of the new three phase 500kV:115kV transformer, one of the largest on the West Coast.
In July when the new transformer was energized, PSE Director of Operations, Ryan Murphy Director of Operations, Ryan Murphy’s remarks included, “The efforts required to design, procure and install this Extra High Voltage (EHV) transformer are truly remarkable.”
Much attention is rightly given to the design, manufacturing, installation and commissioning of EHV transformers. The processes and practices PSE crews used to prepare the new pad site, ensured that active component connections are correct and that the transformer protection and monitoring systems are operational were “truly remarkable”. But Murphy’s statement was also about the final transporting, handling and delivery of the massive transformer to the Tono Substation job site.