ID 3206886 © Vladimir Konjushenko | Dreamstime.com
Substation id 3206886 © Vladimir Konjushenko | Dreamstime com

FirstEnergy’s ATSI Seeks Ohio Regulatory Approval Of Estimated $23.1m, 138-kV Project

April 26, 2021
As noted in the filing, the new approximately five- to six-mile line would run through the cities of Campbell and Youngstown in Mahoning County, Ohio, connecting the Lincoln Park substation to the Riverbend substation.

FirstEnergy’s American Transmission Systems, Inc., (ATSI), on April 16 filed with the Ohio Power Siting Board an application for a certificate of environmental compatibility and public need for the Lincoln Park-Riverbend 138-kV Transmission Line Project.

As noted in the filing, the new approximately five- to six-mile line would run through the cities of Campbell and Youngstown in Mahoning County, Ohio, connecting the Lincoln Park substation to the Riverbend substation. The project would begin at the existing Lincoln Park substation and trend southwest for about two miles, and then west for about three miles, to the Riverbend substation. ATSI added that the single-circuit line would be primarily supported on wood or steel poles requiring a 65-foot-wide permanent right of way (ROW).

The company noted that the project’s preferred route, “Route 44,” is about 5.21 miles long. The estimated applicable intangible and capital costs of the preferred route total about $23.1m, the company said.

The project also involves work at the Lincoln Park and Riverbend substations, ATSI said, noting that at the Riverbend substation, for instance, the substation fence would be expanded to accommodate the conversion of the 138-kV straight bus to a four-breaker ring bus. At the Lincoln Park substation, the bus would be expanded to accept the new 138-kV transmission line terminal.

ATSI also noted that while the work at the Riverbend substation meets board requirements and is included as part of the application, work at the Lincoln Park substation would occur inside the substation fence and is not part of the application.

To read the complete article, visit TransmissionHub.

Voice your opinion!

To join the conversation, and become an exclusive member of T&D World, create an account today!