BOLD is a compact, high-capacity transmission line designed for increased power transfer.

Asia Eyes Transmission Capacity Expansion

May 7, 2021
Economic and social developments have accelerated the energy transition in Asia, opening the door to new transmission line technologies.

When expanding transmission systems, acquiring the land for new lines is often a prerequisite. As is the case in numerous countries, rights-of-way (ROW) in Southeast Asia are crowded and utilities are finding it increasingly challenging to acquire new ROW for transmission lines, particularly in heavily populated areas. The challenges are typically around space constraints and concerns about the line design aesthetics, especially with higher-voltage lines that deliver bulk power more efficiently over long distances.

In a 2019 Southeast Asia Energy Outlook report, the International Energy Agency (IEA) noted that energy demand in this region has increased by more than 80% since 2000, marking its trajectory as among the fastest growth rates in the world. The IEA goes on to predict this growth shows no signs of slowing down, as it is being driven by rising incomes, industrialization and urbanization. The organization estimates that by 2040, the region’s energy demand will increase by an additional 60%, the economy will more than double in size and the population will grow by an additional 120 million people, mostly in urban areas.

With growth indicators like these, Asia’s power leaders are intensifying efforts to increase the region’s transmission capacity. In addition to adding more renewable energy and battery energy storage systems to their network, Southeast Asia utilities also are looking closely at transmission line technology. One solution under consideration is the Breakthrough Overhead Line Design (BOLD). U.S. utility American Electric Power Co., Inc. (AEP) is using this compact, low-profile line design to overcome the same transmission challenges as those faced by Southeast Asia and many other utilities around the world.

A ROW Challenge

In 2019, Google joined fellow technology leaders Amazon and Facebook by breaking ground on a US$600-million, 400-acre (162-hectare) data center in New Albany, Ohio, U.S. It is a calculated economic strategy, with the city encouraging investment from information technology operations and businesses that complement the data hubs, including call centers and corporate offices. The city of New Albany, Ohio, U.S., is a rapidly growing suburb 15 miles (24 km) northeast of the state capital, Columbus. Part of AEP’s service territory, central Ohio is home to at least 50 data centers — nearly half of the state’s 120 data centers — representing billions of dollars in investments. Nine of these data center projects reside in New Albany.

With this data center development under way, it became more critical than ever to ensure the reliable, resilient flow of power to these facilities.

AEP has high-capacity infrastructure in the area connected to its 11-state transmission system. The existing communication capacity and New Albany’s city infrastructure makes this a high-value location for data centers. For AEP to reliably serve these large loads, new substations and additional transmission system capacity were required, but the availability of ROW for new transmission lines was extremely limited.

To meet the infrastructure improvement, AEP decided to use BOLD technology on an existing single-circuit 345-kV overhead transmission line. Comprised of 40 transmission structures made of wood and laminated wood, the transmission line was installed in the 1970s and nearing its end of life. It needed to be renewed or replaced.

Key Design Differences

This was not AEP’s first experience with BOLD. In fact, the utility developed the technology to overcome transmission challenges like the difficulty in getting new lines sited. AEP teamed up with Hubbell Power Systems and Valmont Industries on some aspects of the development to ensure the design met performance requirements and had the necessary structures, insulators and hardware for installation.

After extensive laboratory testing, the utility was ready to use the new line design in its transmission system. The first use of BOLD was in 2016 on a 22-mile (35-km), 138-kV rebuild with a 345/138-kV hybrid line design in Fort Wayne, Indiana, U.S.

The BOLD solution features a streamlined, low-profile structure with phase-conductor bundles arranged in compact delta configurations. An arched crossarm on the structure supports circuits set at the top of a tubular steel pole, which AEP feels makes for a nicer appearance than traditional design. BOLD can support both single-circuit and double-circuit lines, and it also can expand single-circuit into double-circuit lines, which is exactly what AEP did to meet the objectives of its New Albany ROW data center project.

The average 100-ft (30-m) 345-kV BOLD structure is about one-third shorter than a traditional double-circuit design. Each phase contains multiple conductor bundles 18 inches to 32 inches (457 mm to 813 mm) in diameter. The distances between the three phases are as low as 14 ft (4.3 m) and maintained using two interphase insulators per circuit. Standard insulators attach each of these bundles to the crossarm and tubular structure bodies. The crossarm supports two shield wires positioned to provide zero-degree shield angle to the outermost phases.

Converting The Corridor

AEP’s existing ROW for the data center project was surrounded by urban and suburban growth, making the prospect of building new lines daunting and tremendously expensive, with New Albany ROW prices around $300,000 per acre. Converting this corridor from a single-circuit to a double-circuit transmission line eliminated the need for an expensive and contentious line routing process. Plus, the utility was able to address an aged asset in need of attention.

This solution doubled the capacity of a valuable existing corridor. As a result of selecting the BOLD transmission line design instead of a traditional design, AEP benefited from significantly increased capacity and more efficient power delivery capability while maximizing an existing ROW.

The smaller footprint and lower structure heights also enabled the utility to shorten the construction timeline, by allowing builders to construct the transmission line with very short-duration outages. The construction process also was expedited by undertaking work at ground level followed by lifting the top sections of the towers, complete with insulators, into place prior to conductor stringing.

The cost comparison between erecting a traditional transmission line and a BOLD transmission line on an existing ROW is influenced by a multitude of factors, such as line length, megavolt-ampere transfer capacity and construction methods. Currently, based on the BOLD lines that have been constructed to date, AEP has found the material and construction costs are similar to that of traditional designs. However, the overall cost of ownership for BOLD lines comes down dramatically, with a up to a 60% increase in load transfer capacity, up to 30% reduction in line losses and the savings associated with constructing a transmission line on the ROW.

System Stability

AEP’s New Albany project and others like it serve as an example for how advanced transmission line technologies can enable utilities, particularly those in Southeast Asia, to meet rising energy demand in an efficient, secure and affordable manner. To address excessive transmission line losses linked to the operation of inefficient and aging transmission systems, Asia’s power leaders are looking to optimize the use of ROW for increased power capacity to meet consumer needs, while allowing for the integration of renewable energy.

Technologies that require smaller footprints reduce land acquisition challenges and enable utilities to generate more revenue from increased power available at the receiving end. There also is an opportunity to combine advanced transmission technologies with data analytics and artificial intelligence to mitigate variable renewable energy generation in support of transmission system stability and smart grids.

To optimize the opportunities in growing transmission system complexities, Asia’s power sector is partnering with leaders who can share global best practices and regional execution experience to mitigate project risks, while developing local resources and expertise in Asia for future projects.

Narsingh Chaudhary is executive vice president and managing director for Black & Veatch’s Asia power business. Chaudhary has leadership responsibility for the power business in Asia and India, where the company focuses on being a global solutions provider with highly skilled professionals that deliver planning, consulting, engineering, construction, program management and combined engineering, procurement and construction solutions to meet clients’ rapidly changing infrastructure needs. Its service offerings include conventional, renewable, and distributed power generation, transmission and distribution, microgrids and behind-the-meter services.

Adrian Tan is vice president and sales director for Black & Veatch’s Asia power business. For more than 20 years, Tan has garnered extensive sales, engineering and operations experience in the power industry across the globe. As vice president, sales and marketing for Asia power business at Black & Veatch, he is responsible for delivering solutions to clients across the full portfolio of power services in conventional, renewable, and distributed power generation, transmission and distribution, microgrids and behind-the-meter services.

For More Information:

BOLD Transmission | www.boldtransmission.com

Hubbell Power Systems | www.hubbell.com

Valmont Industries | www.valmont.com

Voice your opinion!

To join the conversation, and become an exclusive member of T&D World, create an account today!