• PB Appointed Employer's Representative For EirGrid East West Interconnector Project

    January 6, 2009, Ireland -- EirGrid plc has appointed international engineering consultancy Parsons Brinckerhoff (PB) as Employer's Representative on the East West Interconnector Project, an HVDC (high voltage direct current) power interconnection ...
    Jan. 8, 2009
    5 min read

    January 6, 2009, Ireland -- EirGrid plc has appointed international engineering consultancy Parsons Brinckerhoff (PB) as Employer's Representative on the East West Interconnector Project, an HVDC (high voltage

    direct current) power interconnection between Ireland and the UK. PB will perform the role

    with its alliance partner, marine environmental design and risk management specialist, Metoc

    plc.

    Linking the electricity grids of Ireland and the UK, the subsea interconnector is being

    developed, and will be owned, by EirGrid, the independent Irish electricity grid operator,

    working closely with the Commission for Energy Regulation in Ireland. The 500 MW

    interconnector will increase security of supply and competition in the Irish electricity market,

    and is due for completion in 2012.

    EirGrid's Project Director, John Fitzgerald, commented on PB's appointment, saying, “We in

    EirGrid look forward to working with Parsons Brinckerhoff in the coming years to meet the

    challenges of delivering this critical infrastructure.”

    PB has been involved in the development phase of the Interconnector project, both as

    Technical Advisor and Civil Engineering Consultant, advising on issues relating to

    procurement, system integration and the UK civil aspects of the project. This new contract,

    signed on Dec. 15, will see PB heavily involved throughout the implementation phase,

    managing the EPC contractor on behalf of EirGrid.

    Tenders are currently being received from major EPC contractors to manufacture, install and

    commission HVDC converter stations, land and subsea cables, and the necessary power

    infrastructure to connect the 400 kV grid in Ireland, where EirGrid is the Transmission

    System Operator and ESB Networks is the Transmission Asset Owner, with the UK 400 kV

    grid operated by National Grid.

    A 400 kV connection at the 400 kV Woodland substation outside of Dublin will be linked to an

    HVDC converter station. From there it will connect via cable to a landing point on the Irish

    coast. A subsea cable will be laid on the bed of the Irish Sea, to be landed on the North

    Wales coast, from where there will be a cable connection an HVDC converter station linked

    to a 400 kV connection at the Deeside substation in North Wales.

    This is the first project undertaken by PB with its alliance partner Metoc plc, who will provide

    project management, technical support and installation representation for all marine

    activities. PB will be supported by two further specialist subconsultants, AndersenPES

    (HVDC technology) and PowerSure Technology (cable technology), who also worked with

    PB during the development stages of the Interconnector.

    PB's cable, overhead line and substation experts have extensive experience in projects of

    this nature, including roles on the Caprivi HVDC Link Interconnector between Namibia and

    Zambia, and the Basslink HVDC subsea interconnector between northern Tasmania and

    mainland Australia.

    The scope of PB's services comprises:

  • Pre-EPC contract phase: review of EPC contract; preparation of project implementation

    plan; setting up systems for EPC contract commencement

  • Post-EPC contract award: design review activities, managing EPC contractor

    performance and payments; manufacturing inspections, witness testing and construction

    supervision for the converter station sites, land cable route and marine elements;

    commissioning supervision

  • Post-takeover support during the reliability run and warranty period

    About Parsons Brinckerhoff:

    About Parsons Brinckerhoff (PB). PB is a global leader in developing and operating

    infrastructure around the world, with around 13,000 employees dedicated to meeting the

    needs of clients and communities across Europe, Africa, the Americas, the Middle East, Asia

    and the Australia-Pacific region. Clients come to PB for a wide range of advice, skills and

    resources in strategic consulting, programme management, planning, engineering,

    construction management and operations. For over a century PB has earned a distinguished

    reputation for delivering world-class infrastructure and its technical expertise in power,

    transportation, community development, water and the environment. www.pbworld.com/ea

    About Metoc plc. Metoc provides environmental design and risk management services to

    add and retain value throughout an asset's life cycle by understanding how the project/asset

    affects, and is affected by, the environment. Metoc is an independent company with over 25

    years' experience in the marine, coastal and river environments for marine cables, renewable

    energy, water, oil & gas, and coastal developments. Over the last 12 years, Metoc has

    provided a life cycle of services on several large-scale cable interconnectors; from initial

    route engineering and assessment to all aspects of the installation and client representation.

    Metoc aims to stand alone, in providing clients with an exemplary service on every project.

    www.metoc.co.uk.

    Contact:

    Natalie Griggs

    Marketing Manager

    (44-(0)1428-727-800

    [email protected]

    About EirGrid plc.

    EirGrid is the independent electricity Transmission System Operator

    (TSO) in Ireland and the Market Operator in the wholesale electricity trading system.

    EirGrid's role is to deliver services to generators, suppliers and customers across the high

    voltage electricity system, and to put in place the grid infrastructure needed to support

    Ireland's economy. EirGrid develops, maintains and operates a safe, secure, reliable,

    economical and efficient transmission system. It plays a key role in the operation of the

    Single Electricity Market, as well as developing key infrastructural projects. www.eirgrid.com

    Contact:

    Maria Laffey, Marketing Communications Manager

    Parsons Brinckerhoff Ltd

    Tel: 44-(0)191-226-2565; e-mail: [email protected]

  • About the Author

    Amy Fischbach

    Field Editor

    Amy Fischbach is the field editor for the Electric Utility Operations section of Transmission & Distribution World. She worked for Prism Business Media (now Penton) for eight years, most recently as the managing editor of Club Industry's Fitness Business Pro magazine. She is now working as a freelance writer and editor for B2B magazines. Amy earned her bachelor's and master's degrees in journalism from Kansas State University in Manhattan, Kansas. She serves as the national vice president of the American Society of Business Publication Editors. She can be reached at [email protected].

    Sign up for TDWorld eNewsletters

    Voice Your Opinion!

    To join the conversation, and become an exclusive member of T&D World, create an account today!