7 The transformer tank and its medium-frequency transformer
LLC switching mode
Each of the nine medium frequency transformers is a part of the associated DC/DC converter ➔ 4. By using the transformer's leakage and magnetizing inductances and the external circuit's capacitors, a resonant LLC circuit is created (Lr, Lm and Cr as shown in ➔ 5). The advantages of an LLC circuit include:
- Wide output-regulation range
- Reduction of switching losses on the primary side through zero voltage switching (ZVS) over the entire load range
- Low turnoff current controlled by the design (not truly zero current switching, ZCS)
- Low-voltage stress and ZCS on the secondary side diode rectifier
- Load-independent operation at resonant frequency
As an LLC circuit is based on the principle of resonance, variation of the switching frequency can be used to control the output voltage. However, in the present PETT implementation, this feature has not been used and the LLC resonant DC/ DC converter operates in the open loop with a fixed switching frequency of 1.75 kHz, which is below the resonant frequency.
The control system
The control targets can be summarized as:
- Maintaining sinusoidal input current
- Near-unity power factor
- Constant average DC-link voltage
- Grid harmonic rejection
The hardware is ABB's AC 800PEC controller, a platform that permits the integration of fast and slow control functions.
The PETT demonstrator on the SBB Ee 933 locomotive
Thanks to a long-term partnership between SBB (Swiss Federal Railways) and ABB, a pilot PETT installation is currently being tested on a type Ee 933 shunting locomotive (➔ title picture). In early 2008, ABB initiated extensive research and engineering work on all subsystems. The PETT demonstrator development came to fruition in spring 2011 and subsequently underwent full electric testing in the laboratory before the pilot was taken into operation.
The existing Ee 933 traction transformer and GTO rectifier were removed to provide space for the new PETT cubicle. Some mechanical adaptations and electronic interface rework was necessary to accommodate the PETT.
The locomotive operates under the 15 kV/16.7 Hz railway grid. The pilot installation was completed in mid-2011, and homologation with the Swiss Federal Office for Transport (FOT) was achieved by the end of the year. The locomotive commenced shunting operation in February 2012 at the Geneva Cornavin station.
The PETT ➔ 8 has nine cascaded modules, of which only eight are essential for operations (the ninth is for redundancy). The unit has 1.2 MW nominal power and can supply 1.8 MW peak for short durations. The DC output voltage is 1.5 kV. The overall weight is 4,500 kg, including cooling. When comparing this with traction transformers of the same power rating, it should be noted that the PETT not only replaces the actual transformer but also the LV rectifier (compare ➔ 2 and ➔ 3).