Basin Electric Cooperative
Screenshot 2023 02 15 101158

Neset-to-Northshore Transmission Project Energized

Feb. 15, 2023
While winter weather caused a slight delay, the project came in under budget. Basin Electric staff supported the right-of-way, permitting, design, material procurement, and construction management for the project.

The Neset-to-Northshore 230-kilovolt (kV) transmission project was energized on Jan. 18. The 27-mile transmission line begins at the existing Neset Substation east of Tioga, North Dakota, and ends at the new Northshore substation south of Ross, North Dakota. According to Bobby Nasset, Basin Electric civil engineering supervisor, the project will provide capacity to serve increasing load growth in the region.

Work on the Northshore substation began in the fall of 2021 and on the transmission line in March of 2022. The project was initially scheduled to be energized in November 2022, but early winter storms slowed down its completion by about two months.

Nasset said this is the first project where Basin Electric used a carbon fiber core conductor in the construction of a transmission line. “Previously, we have used aluminum conductor with steel reinforcement. The steel provides good tension strength but it expands with increased temperature, causing the conductor to sag and it limits the current carrying capacity of the transmission line,” he said. “Carbon fiber does not expand under heat, which reduces the sag under higher loading conditions. With this conductor material, we were able to reduce the number of structures needed for the project while still meeting the capacity goals.”

The Northshore substation provides a delivery point for Basin Electric Class C member Mountrail-Williams Electric Cooperative, which will interconnect four 115-kV circuits. Nasset said coordination with Mountrail-Williams Electric went very smoothly and he and his team are thankful for their assistance in the overall project.  

While winter weather caused a slight delay, the project came in under budget. Basin Electric staff supported the right-of-way, permitting, design, material procurement, and construction management for the project.

The project is one of five identified and approved by the Southwest Power Pool (SPP) and summarized below. The Neset-to-Northshore project was identified through SPP’s Load Interconnection process and is needed to support load growth specific to the Parshall, North Dakota, area.

SPP identified three projects through its Integrated Transmission Planning (ITP) study. SPP’s ITP study is done annually, and assesses the five- and 10-year reliability, economic, and policy needs of the transmission system. When needs are identified, stakeholders such as Basin Electric submit projects that mitigate the needs in the system. SPP compiles a portfolio of projects that are approved by its board and then assigned to the stakeholders that submitted the projects. The projects, approved by Basin Electric directors, include:

  • Leland Olds Station-to-Tande 345-kV transmission project, which includes 175-miles of 345-kV transmission line and a new 345/115-kV substation. Pending easement acquisition and permitting, the project goal is to energize in 2025. The line will originate at the Leland Olds Station near Stanton, continue around the east end of Lake Sakakawea, and travel west to the Tande substation near Tioga.
  • Roundup-to-Kummer Ridge 345-kV transmission line, a 35-mile line north of Killdeer is set to be energized in 2025. Final energization date will depend on easement acquisition and permitting.
  • East Fork 345/115-kV substation near Wheelock, which will intersect an existing transmission line and add a new delivery point for Basin Electric Class C member Mountrail-Williams Electric Cooperative, is set to be energized in 2024.The fifth project, identified by SPP’s Aggregate Transmission Service process, is required to provide additional transmission capability into Saskatchewan, Canada.
  • Wheelock-to-Saskatchewan and Tande-to-Saskatchewan, 230-kV transmission lines, will connect to SaskPower transmission equipment at the Canadian border. The lines are approximately 50 and 60 miles in length, respectively. Basin Electric is the designated transmission owner for the upgrade in the United States, and SaskPower will complete the circuit within Canada. The project will provide export and import capabilities of up to 650 megawatts of electricity, strengthening the local and regional electric system.

The five projects represent an investment of nearly $725 million in high-voltage transmission infrastructure in western North Dakota.

Todd Telesz, Basin Electric chief executive officer and general manager, said providing reliable electricity is a priority. “As western North Dakota grows, the electric transmission grid must grow with it, and Basin Electric is committed to serving our members as their need for electricity continues to increase,” Telesz said. “This commitment, along with our all-of-the-above strategy for generating electricity to include natural gas, coal, wind, recovered energy generation, market purchases, and soon solar, ensures we provide reliable, affordable, and responsible electricity. Basin Electric’s membership has supported energy booms across our service territory and our cooperative network of distribution, generation, and transmission has built and continues to support what our nation needs to thrive.”

For the Leland Olds Station-to-Tande and Roundup-to-Kummer Ridge transmission lines, Basin Electric’s right-of-way team is in contact with landowners to determine the preferred routes of the lines. The right-of-way team will begin contacting landowners regarding the Wheelock- and Tande-to-Saskatchewan lines in the coming weeks. Basin Electric must secure permits and authorizations from federal, state, and local jurisdictions such as counties and townships before construction may begin.

Voice your opinion!

To join the conversation, and become an exclusive member of T&D World, create an account today!