Commission Signals Approval for Badger Coulee Transmission Line Project

March 26, 2015
PSC commissioners verbally approve Northern Route at open meeting; final order will be issued by April 24, 2015

Following more than four years of public involvement and regulatory review, the merits of the 345,000-V Badger Coulee Transmission Line Project were discussed today by the Public Service Commission of Wisconsin. At an open meeting, the PSC commissioners agreed with the project’s need and benefits outlined by American Transmission Co. and Xcel Energy for the approximately 180-mile line, which will electrically connect the La Crosse area to northern Dane County. The next step is for the Commissioners’ discussion to be documented in a written order and then approved by the Commissioners at an open meeting before April 24, 2015.

“We appreciate the public’s active involvement throughout our public outreach and the regulatory review process,” said ATC Manager of Environmental and Local Relations Greg Levesque. “Public input helps identify ways to avoid and minimize environmental and community impacts. We will continue to communicate with affected property owners and communities in the years to come to ensure the safe construction of the line.”

During the meeting, PSC commissioners selected the Northern Route, which was one of the two options submitted by the applicants. More than 90 percent of the Northern Route uses existing utility and Interstate or U.S. highway corridors. The project’s end points are Xcel Energy's new Briggs Road Substation near Holmen and ATC’s North Madison Substation in the Town of Vienna, continuing to ATC’s Cardinal Substation in the Town of Middleton. The PSC’s order for the project, including any minor route adjustments or conditions ATC and Xcel Energy must meet to construct the project, will be issued by April 24, 2015.

This project has been designated a Multi-Value Project by the Midcontinent Independent System Operator because it will enable the delivery of energy in support of reliability, economic and public policy benefits. The $580 million estimated project cost will be shared among all electric users in MISO’s footprint, which includes 15 Midwestern states and the Canadian province of Manitoba.  

“We are pleased that the PSC has recognized the need for and benefits of this project.” said Xcel Energy Manager, Regional Transmission Initiatives Kyle Neidermire. “This project will help ensure electric reliability and provide access to lower-cost power and renewable energy for all electric users in the region.”

ATC and Xcel Energy will begin reaching out to impacted property owners along the selected route this year. Project construction is expected to begin in 2016 to meet an in-service date of 2018.
 

A map of the proposed route options and additional project information are available at www.BadgerCoulee.com

Voice your opinion!

To join the conversation, and become an exclusive member of T&D World, create an account today!