Chongqing Electric Re-Conductors with 3M ACCR to Ensure Power Supply for Olympics

Aug. 7, 2008
Chongqing Electric Power Corp. has become the second major utility in the People’s Republic of China to install the 3M Aluminum Conductor Composite Reinforced (ACCR) to boost transmission capacity on a key line without the need to build larger transmission towers

Chongqing Electric Power Corp. has become the second major utility in the People’s Republic of China to install the 3M Aluminum Conductor Composite Reinforced (ACCR) to boost transmission capacity on a key line without the need to build larger transmission towers. The utility says it needed extra capacity to meet anticipated heavy power demand for the summer Olympics in Beijing and did not have time to construct new towers.

This installation will serve more than a half-million residents within two districts in Chongqing City, an ancient city with a population of approximately four million, located on the Yangtze River in southwest China, within Sichuan Province.

In late 2007, Shanghai Electric became the first utility outside of the United States to install the 3M ACCR. Since then, utilities in Canada and Brazil also have chosen 3M’s breakthrough conductor to enlarge capacity on lines where new construction would pose economic or environmental problems. Fourteen utilities in the U.S. so far have deployed 3M ACCR, which can carry more than twice the power of conventional steel conductors of the same diameter.

Using existing towers, Chongqing Electric has installed a two-circuit line of approximately 3.4 miles (5.5 km), linking the Shuinian and Shuangshan substations. Chongqing is in a subtropical region with high humidity and frequently extreme summer heat, and 3M ACCR was chosen in part because of its proven reliability in difficult climates.

“This is one of the hottest cities of China, with monsoonal weather, and we required a conductor that could be relied upon to carry more current under those conditions, and could be installed quickly and reliably within the existing infrastructure,” explains Wang Xinkuan, chief design engineer for Chongqing Electric Power Corp. Installation required only two weeks, he adds.

“3M ACCR has been in use, both in continuous field tests and commercial operation, for several years and around the world, under a wide range of harsh climate conditions,” says Tim Koenig, director of the 3M High Capacity Conductor Program. “The conductor has met all performance and reliability expectations with no failures in the field, in either installation or operation.”

Voice your opinion!

To join the conversation, and become an exclusive member of T&D World, create an account today!