Resources

On Demand Media

Demand Viewing

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

White Papers

Designing Energy Services for Commercial and Industrial Customers

Over the past year, technology advances and high energy prices have stimulated interest in Advanced Metering Infrastructure (AMI). Discussions are wide-ranging. Some focus globally: Australian and Canadian “smart metering”, new European Union requirements, the results of time-of-use pilots that arose in the wake of California’s deregulation debacle.

More White Papers

Marketplace Ads

  • Trip Wire

    Automate NERC Cyber Security Compliance

  • Ike Blog

    Reports From The Front

Case Studies

York Region Finishes Tasks Faster

We all know that data integration improves productivity and York Region is living proof. Using AutoCAD® Map 3D, York saved time and money by relying on its AutoCAD-trained staff to quickly implement a new system that incorporates both CAD and GIS.

Save Time with CAD and GIS Integration

Read how the Public Works Department of the City of Tacoma (Tacoma), Washington, uses its geospatial data to do everything from issuing building permits and managing waste water to maintaining streetlights


         Subscribe in NewsGator Online   Subscribe in Bloglines  

China Bridges Power From the Mainland

The Famous Shanghai Yangshan Deepwater Harbor is located in the small Yangshan Island sea area east of Hangzhou Bay and southeast-east Shanghai. The harbor is connected to the mainland of Shanghai by the Donghai Bridge, which is 32.5 km (20 miles) long.

To satisfy the harbor's maximum demand of 130 MW (120 MVA), 110-kV cables were on the bridge to connect the harbor to the mainland. Shanghai Electric Power Co. began the design work in 2003, and completed the associated construction work on the bridge for the cable installation in 2005.

The project included two circuits, each having a 38-km (24-mile) route of which 25 km (15.6 miles) is on the bridge, making it one of the longest cable systems installed on a bridge in the world. Table 1 shows the key parameters of the project.

PROJECT FEATURES

The Donghai Bridge is an important highway with four lanes plus an additional two lanes for backup. The various sections of the bridge structure that had to accommodate the 110-kV cables are described in Table 2. The Shenyang Furukawa Cable Corp. Ltd. was awarded the cable-supply contract. Cross-linked polyethylene (XLPE)-insulated cable was selected for its superior electrical performance and ease of installation.

To avoid mechanical damage that may occur due to changes in cable temperature, snaking of the cable was used on the bridge. Because the cable is installed in the box girder of the bridge and the duct platform, the cable installation was affected by the complex structure of the bridge. As a result, different wavelengths for the snaking were used to satisfy the condition. The wavelengths varied from 5 m to 9 m (16 ft to 30 ft).

DESIGNING FOR LONGITUDINAL DISPLACEMENT AND ANGULAR DEFLECTION

Unlike conventional buried cable, longitudinal displacements (due to temperature changes), the vehicular load and wind will affect the cable installed on a bridge. The value of this displacement is significant and varies according to the type of bridge structure as shown in Table 2. Special measures have been adopted at each end of the bridge.

When the bridge is in service, it is affected by the traffic loads and weather conditions. To absorb longitudinal displacements, cable offset devices are installed at each end of the bridge. These devices overcome the problems of bridge displacement by varying the contour of cables.

When designing cable offset devices, the design of the bridge must be considered to ensure the shape and design of the cable offset devices can be installed. It is also important to consider the fatigue characteristics of the cable's metallic sheath.

The specified cable bending radius should be satisfied. But in order to allow for the continuous distortion of the cable device, the specified cable bending radius needs to be increased. To allow for the maximum bridge expansion, the bending radius on the Donghai Bridge is some 30 × D, where D is the average diameter of the metallic sheath.

It would have been difficult to make the cable in the offset devices move smoothly if the cables were not fixed. Therefore, the cables are fixed at the middle of each device with the movable structure. Also, the sliding system and uniform action device for the cable expansion was set in the stayed-cable sections of the bridge, where the expansion and cable displacement are greatest.

BENDING AND VIBRATION

The end of the bridge is designed to allow for vehicular loading on the stayed-cable sections of the bridge, which results in a slight angle where the bridge is anchored. Normally this displacement is not a problem with the angle being less than 2 degrees. The cable can withstand this bending, but the steel used for the offset devices is distorted. As a result, the special bending device is an integral part of the cable offset device on the stayed-cable bridge. Two hinge joints are set at the end of the offset device so that the steel bracket of the device can rotate in any direction.

The frequency and magnitude of the vibration in bridges differs according to the structure, shape and loading conditions. The vibration has two components. First is a uniform low-frequency vibration, less than 1 Hz, which is a function of the bridge length and rigidity. The second component is the vibration generated by vehicle movement. To minimize the effect of these vibrations on the Donghai project, an aluminum-sheath cable was used because it is superior to a lead-sheath cable in conditions subject to vibration. Additionally, correct spacing of the cable support brackets prevent resonance between the cable and bridge.

The formula used to determine the optimum spacing is:

L≤[???·(EI·g/W)1/2/2f]1/2,

where f = bridge frequency, EI = bending rigidity, g = acceleration of gravity and W = cable weight.

The distance between cable brackets based on this formula was less than 2 m (6.5 ft) so the spacing on the Donghai Bridge varies between 1.5 m to1.6 m (4.9 ft to 5.2 ft). Rubber pillows are placed under the brackets to absorb most of the vibration energy; rubber layers used in the cable clamps have the same effect.

The position of cable joints is critical to prevent the adverse effect of bridge vibration; therefore, the positions of joints were near the bridge piers, the points of least vibration.

CABLE GROUNDING ON THE BRIDGE

The bridge piers were chosen as the grounding pole for the cable to minimize the earth resistance, reduce the grounding material required and balance the electric potential. On the Donghai Bridge, the measured value of the earth resistance is about 0.2 Ω, less than 1 Ω required by the designer. The values of touch voltage and dangerous voltage are within the specified limits.

To ground the metal sheath of the cable, the length of the cable was divided into segments to reduce the number of cable joints; the maximum length between segments was 930 m (3051 ft) with all segments more than 800 m (2625 ft) long. Under the maximum load conditions, the induced voltage on the metal sheath is about 92 V, so the sheath is cross-bonded, surge-voltage limiters are installed and the neutral point is directly earthed.

By employing cross-bonding, the induced voltage, touch voltage and dangerous voltage can be limited effectively, and as the value of induced voltage on adjacent cables is low, there is no need to install a special return path adjacent to the cable. The calculation of transient single-phase short-circuit conditions indicates that the overvoltage can be reduced by 20% due to the effect of the reinforcing steel components on the bridge.

SUCCESSFUL INSTALLATION

Construction of the bridge started in August 2004 and was completed in 15 months. The cable installation work, undertaken by the Shanghai Cable Transmission & Distribution Co., was completed concurrently with the bridge construction. On completion to guarantee the quality of the cable system, a 24-hour no-load test was conducted and partial-discharge measurements were taken on all joints after one month's operation of the circuits.

The Shanghai Electric Power Co. has succeeded in designing and installing one of the world's longest high-voltage cable circuits on a bridge in a project that cost some US$55 million. The utility solved the problems that could cause damage to the cables, namely expansion and vibration, and developed and installed an effective means of grounding the circuits.


Meng Yu graduated from Shanghai Jiao Tong University in August 1996 and joined the Shanghai Electrical Power Design Institute in September 1996. Currently, Yu is chief engineer of the Power Transmission Department, where he is engaged in the design and research of transmission lines.
mengy@sepd.com.cn

Gong Zun graduated from Shanghai Jiao Tong University in August 1983, and joined Shanghai Cable Transmission & Distribution Co. in September 1983. Currently, he is board chairman of the Shanghai Electrical Power Design Institute, where his main responsibilities are the research and design of power cable transmission.

Table 1. Key Cable System Parameters
Type of cable 110-kV single-core XLPE-insulated cable
Conductors Copper
Cross-sectional area 630 mm2 (1 inch2)
Cable length 25 km (15.6 miles) installed on the bridge
13 km (8.13 miles) installed at the land shore
Accessories Prefabricated insulating joints — 312 sets
GIS joints — 12 sets
Circuit transfer capacity 103 MW

Table 2. Type of Cable Installation on the Different Bridge Sections
Type of bridge section Length Maximum value of expansion Type of cable installation
Concrete box girder of the bridge
Cable route section A
22 km
(13.8 miles)
+200 mm, -200 mm
(+7.87 inches, -7.87 inches)
Installed inside the box girder at the horizontal snake shape
PVC /PE duct platform (spanned between two box girders) 1.54 km
(0.96 miles)
+150 mm, -150 mm
(+5.91 inches, -5.91 inches)
Installed on the special PVC/PE duct platform (with the water pipes and communication lines) at the horizontal snake shape
Donghai
stayed-cable bridge
0.83 km
(0.52 miles)
+380 to 440 mm
(+15 to 17.3 inches)
Installed inside the steel structure box girder in the horizontal snake shape
Kezhushan
stayed-cable bridge
Cable route section D
0.63 km
(0.39 miles)
+480 mm, -480 mm
(+18.9 inches, -18.9 inches)
Installed on the special platform for cable at the trefoil snake shape

Table 3. Cable Cross-Section Dimensions
Figure number Item Dimension
mm (inches)
Diameter of conductor 30.3±0.3 (1.19±0.011)
Thickness of inner screen 1.0 (0.04)
Insulation thickness 17.0 (0.67)
Thickness of outer screen 1.0 (0.034)
Diameter of insulation 67.9 +1.5, -1.0
(2.67 + 0.06. -0.04)
Diameter of metal sheath 90.3±2.0
(3.56±0.08)
(aluminum)
82.1±2.0
(3.23±0.08)
(lead)
Thickness of outer screen 5.0 (PVC)
(0.196)
5.0 (PE)
(0.196)
Diameter of cable 100.3±2.0
(3.95±0.08)
93.3±2.0
(3.67±0.08)
Weight of cable (kg/m) 13.96 22.35


Commenting terms of use

Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.

General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.

blog comments powered by Disqus

Want to use this article? Click here for options!
© 2008 Penton Media Inc.

Most Read

Community

Hurricane Ike Coverage

Hurricane Ike Coverage
On September 12th, Hurricane Ike tore through the Gulf Coast, wreaking havoc on lives and property. Transmission & Distribution World’s Rick Bush is headed to the region to provide a first-hand account of the damage including an insider view of utility emergency-response efforts. His reports and subsequent feature coverage will highlight how utilities, contractors and suppliers work as a team to restore power as quickly as possible.
Read Rick’s Blog, Ike: Reports from the Front

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.

Webcasts

ACSS and HS285 Extend Grid Capacity

Sponsored by Southwire

There are capacity bottleneck situations, where new overhead transmission line construction is not a practical reality. In some of these situations overhead lines are in place and they are not able to provide the transfer capacity needed.

Register Now!


Supercondutor Cable Systems

Sponsored by American Superconductor

Transmission & Distribution World presents Superconductor Cable Systems, A Part of the Increasing Bulk Power Transfer Series.

Register Now!


Evolution of Next Generation Wireless Communications in Power Delivery

Sponsored by Alcatel-Lucent

Evolution of Next Generation Wireless Communications in Power Delivery - seeing wireless communications solutions emerge to enable more efficient operations.

Register Now!

More Webcasts

Featured Activity

T&D World University 2008

Get expanded education, practical experience and unprecedented networking in 3 days at T&D World University, the Continuing Education Program for Utility Management, Engineers and Technical Professionals. October 27-29, 2008, Dallas, TX. With CEU-Earning Seminars, Specialized Tracks, 59+ Courses, T&D allows you to maximize your time, with minimal work interruptions. Bring your team to this productive learning environment.

Jobzone
  • October Issue
  • September Issue
  • August Issue
  • July Issue
  • June Issue
  • May Issue
  • April Issue

Browse Back Issues